Global transmission capacity was estimated to have reached 19,883,744MVA by the end of 2021 and is forecasted to grow to 27,052,399MVA by 2027. Russia had 360,948MVA of capacity in 2021 and this is expected to rise to 388,778MVA by 2027. Listed below are the five largest transmission projects by capacity in Russia, according to GlobalData’s power database. GlobalData uses proprietary data and analytics to provide a complete picture of the global transmission segment. Buy the latest transmission substation project profiles here.

1. Altai Substation

Altai Substation is a 1150kV substation located at Altai, Altai Krai, Russia. The substation is under construction and is expected to be commissioned in 2023. The Altai Substation will be operated by Federal Grid Company – Rosseti.

The designed voltage level of the substation is 1150kV and the operating voltage level is 1150kV. The step in voltage of the project is 1,150kV.

Altai Substation is owned by Federal Grid Company – Rosseti. Buy the profile here.

2. Itatsky Substation

Itatsky Substation is a 1150kV substation located at Itatsky, Kemerovo, Russia. The substation is under construction and is expected to be commissioned in 2023. The Itatsky Substation will be operated by Federal Grid Company – Rosseti.

The designed voltage level of the substation is 1150kV and the operating voltage level is 1150kV. The step in voltage of the project is 1,150kV.

Itatsky Substation is owned by Federal Grid Company – Rosseti. Buy the profile here.

3. Belozerskaya Substation – Upgrade – 750/500 kV

Belozerskaya Substation – Upgrade – 750/500 kV is a 750/500kV substation located at Belozerskaya, Russia. The substation is planned and is expected to be commissioned in 2024. The Belozerskaya Substation – Upgrade – 750/500 kV will be operated by Federal Grid Company – Rosseti.

The designed voltage level of the substation is 750/500kV and the operating voltage level is 750/500kV. The step in voltage of the project is 750kV and the step out voltage is 500kV.

Belozerskaya Substation – Upgrade – 750/500 kV is owned by Federal Grid Company – Rosseti. Buy the profile here.

4. Novobryanskaya Substation – Upgrade – 750 kV

Novobryanskaya Substation – Upgrade – 750 kV is a 750kV substation located at Novobryanskaya, Pirogova, Russia. The substation is under construction and is expected to be commissioned in 2023. The Novobryanskaya Substation – Upgrade – 750 kV will be operated by Federal Grid Company – Rosseti.

The designed voltage level of the substation is 750kV and the operating voltage level is 750kV. The step in voltage of the project is 750kV.

Novobryanskaya Substation – Upgrade – 750 kV is owned by Federal Grid Company – Rosseti. Buy the profile here.

5. Vladimir Substation – Upgrade – 750 kV

Vladimir Substation – Upgrade – 750 kV is a 750kV substation located at Vladimirovka, Vladimir Oblast, Russia. The substation is planned and is expected to be commissioned in 2024. The Vladimir Substation – Upgrade – 750 kV will be operated by Federal Grid Company – Rosseti.

The designed voltage level of the substation is 750kV and the operating voltage level is 750kV. The step in voltage of the project is 750kV. Upon completion, the substation will be able to operate at 5MVA.

Vladimir Substation – Upgrade – 750 kV is owned by Federal Grid Company – Rosseti. Buy the profile here.

For more details on the latest transmission substation projects, buy the project profiles here.