Tous (Ferdowsi) Combined Cycle Power Plant is a 1,434MW gas fired power project. It is located in Razavi Khorasan, Iran. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in May 2007. Buy the profile here.
Description
The project is developed and owned by MAPNA Tous Power Generation.
It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is natural gas. In case of shortage of natural gas the plant can also run on Gas Oil.
Development status
The project got commissioned in May 2007.
Power purchase agreement
The power generated from the project is sold to Tavanir under a power purchase agreement.
Contractors involved
MAPNA Power Plants Construction and Development was selected to render engineering procurement construction services for the Tous (Ferdowsi) Combined Cycle Power Plant (Tous (Ferdowsi) Combined Cycle Power Plant Steam Turbine).
Tous (Ferdowsi) Combined Cycle Power Plant ( Tous (Ferdowsi) Combined Cycle Power Plant Gas Turbine Unit I) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Tous (Ferdowsi) Combined Cycle Power Plant ( Tous (Ferdowsi) Combined Cycle Power Plant Gas Turbine Unit II) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Tous (Ferdowsi) Combined Cycle Power Plant ( Tous (Ferdowsi) Combined Cycle Power Plant Gas Turbine Unit III) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Tous (Ferdowsi) Combined Cycle Power Plant ( Tous (Ferdowsi) Combined Cycle Power Plant Gas Turbine Unit IV) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Tous (Ferdowsi) Combined Cycle Power Plant ( Tous (Ferdowsi) Combined Cycle Power Plant Gas Turbine Unit V) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Tous (Ferdowsi) Combined Cycle Power Plant ( Tous (Ferdowsi) Combined Cycle Power Plant Gas Turbine Unit VI) is equipped with MAPNA Turbine Engineering & Manufacturing MGT-70 gas turbine. The phase consists of 1 gas turbine with 159MW nameplate capacity.
Tous (Ferdowsi) Combined Cycle Power Plant (Tous (Ferdowsi) Combined Cycle Power Plant Steam Turbine) is equipped with MAPNA Turbine Engineering & Manufacturing E type steam turbines. The phase consists of 3 steam turbines with 160MW nameplate capacity.
MAPNA Generator Engineering & Manufacturing supplied electric generator for the project.
MAPNA Turbine Engineering & Manufacturing supplied steam boiler for the Tous (Ferdowsi) Combined Cycle Power Plant (Tous (Ferdowsi) Combined Cycle Power Plant Steam Turbine).
For more details on Tous (Ferdowsi) Combined Cycle Power Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.