Talwandi Sabo Thermal Power Project is a 1,980MW coal fired power project. It is located in Punjab, India. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in July 2014. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Talwandi Sabo Thermal Power Project

Buy the Report

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project was developed by Vedanta and is currently owned by Talwandi Sabo Power with a stake of 100%.

It is a Steam Turbine power plant. The fuel is procured from Mahanadi Coalfields Limited, Coal India Limited.

Development status

The project got commissioned in July 2014.

Power purchase agreement

The power generated from the project is sold to Punjab State Power under a power purchase agreement for a period of 25 years. The contracted capacity is 1,980MW.

Contractors involved

SEPCO Electric Power Construction was selected to render engineering procurement construction services for the coal fired power project.

Dongfang Electric (India) was selected as the turbine supplier for thermal power project. The project consists of 3 units of Three Cylinder, With Reheat And Regenerative Cycle & Nozzle And Throttle Governed turbines, each with 660MW nameplate capacity.

Dongfang Electric (India) supplied Hydrogen-Cooled electric generator for the Talwandi Sabo Thermal Power Project (Talwandi Sabo Thermal Power Project Unit I).

Dongfang Electric (India) supplied Hydrogen-Cooled electric generator for the Talwandi Sabo Thermal Power Project (Talwandi Sabo Thermal Power Project Unit II).

Dongfang Electric (India) supplied Hydrogen-Cooled electric generator for the Talwandi Sabo Thermal Power Project (Talwandi Sabo Thermal Power Project Unit III).

Harbin Boiler supplied steam boiler for the Talwandi Sabo Thermal Power Project (Talwandi Sabo Thermal Power Project Unit I).

Harbin Boiler supplied steam boiler for the Talwandi Sabo Thermal Power Project (Talwandi Sabo Thermal Power Project Unit II).

Harbin Boiler supplied steam boiler for the Talwandi Sabo Thermal Power Project (Talwandi Sabo Thermal Power Project Unit III).

STEAG Energy Services (India) is the O&M contractor for thermal power project. The operation and maintenance contract commenced from 2017, for a period of 5 years.

For more details on Talwandi Sabo Thermal Power Project, buy the profile here.

About Vedanta

Vedanta Ltd (Vedanta), formerly Sesa Sterlite Limited, is a diversified metal and mining company. The company, along with its subsidiaries, focuses on the exploration, mining, processing, and exporting of natural resources, power, and oil and gas businesses. Its product portfolio includes lead, zinc, silver, copper rod and cathodes, aluminum, iron ore, commercial power, steel, nickel and copper and oil and gas across India. It also carries out the production of pig iron and metallurgical coke. The company also provides support activities, such as shipping, port services and shipbuilding. It has operations in the US, Asia-Pacific, Europe, the Middle East, and Africa. Vedanta is headquartered in Mumbai, Maharashtra, India.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.