NOVEC Energy Production Halifax County Biomass Plant is a 49.9MW biopower project. It is located in Virginia, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in September 2013. Buy the profile here.
Description
The project was developed by NOVI Energy and is currently owned by Northern Virginia Electric Cooperative.
The project supplies enough clean energy to power 16,000 households.
NOVEC Energy Production Halifax County Biomass Plant is a co-firing project. Wood waste which is a kind of wood by-product is used as a feedstock to power the project.
Development status
The project got commissioned in September 2013.
Contractors involved
Fagen was selected to render engineering procurement construction services for the biopower project.
Alstom Power was selected as the steam turbine supplier for the project. The company provided 1 unit of GRT Turbine turbine with 55MW nameplate capacity.
For more details on NOVEC Energy Production Halifax County Biomass Plant, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.