Matanogawa is a 1,200MW hydro power project. It is located on Hino, Matano river/basin in Tottori, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 1978 and subsequently entered into commercial operation in 1986. Buy the profile here.
Description
The project is currently owned by The Chugoku Electric Power.
Matanogawa is a pumped storage project. The hydro reservoir capacity is 7.94 million cubic meter. The net head of the project is 489m.
The project has 4 electric generators installed at the site.
Development status
The project construction commenced in 1978 and subsequently entered into commercial operation in 1986.
Contractors involved
Hitachi Mitsubishi Hydro was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines, each with 300MW nameplate capacity.
For more details on Matanogawa, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.