Lower Cetin is an 116MW hydro power project. It is planned on Botan river/basin in Siirt, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the under construction stage. It will be developed in a single phase. The project construction is likely to commence in 2011 and is expected to enter into commercial operation in 2024. Buy the profile here.
Description
The project is being developed by Cetin Enerji and is currently owned by Limak Enerji with a stake of 100%.
The gross head of the project will be 35m. The project is expected to generate 300 GWh of electricity.
Development status
The project construction is expected to commence from 2011. Subsequent to that it will enter into commercial operation by 2024.
Contractors involved
Andritz Hydro will be the turbine supplier for the hydro power project. The company is expected to provide 2 units of kaplan turbines, each with 58MW nameplate capacity.
Indar Electric is expected to supply 1 electric generator for the project. The generator capacity is likely to be 4.22 MVA.
For more details on Lower Cetin, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.