Lawrence Energy Center is a 566MW coal fired power project. It is located in Kansas, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in January 1955. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Lawrence Energy Center

Buy the Report

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by Evergy with a stake of 100%.

It is a Steam Turbine power plant. The power plant run on dual-fuel. The primary fuel being used to power the plant is subbituminous. In case of shortage of subbituminous the plant can also run on Natural Gas. The fuel is procured from Arch Coal, Inc., Powder River Basin, Southern Star Central Gas Pipeline.

The project generated 3,345,781MWh of electricity.

Development status

The project got commissioned in January 1955.

Contractors involved

Lawrence Energy Center (Lawrence Energy Center Unit I) is equipped with GE Power steam turbine. The phase consists of 1 steam turbine with 49MW nameplate capacity.

Lawrence Energy Center (Lawrence Energy Center Unit II) is equipped with Siemens Energy steam turbine. The phase consists of 1 steam turbine with 114MW nameplate capacity.

Lawrence Energy Center (Lawrence Energy Center Unit III) is equipped with Siemens Energy steam turbine. The phase consists of 1 steam turbine with 403MW nameplate capacity.

GE Power supplied electric generator for the Lawrence Energy Center (Lawrence Energy Center Unit I).

Siemens Energy supplied electric generator for the Lawrence Energy Center (Lawrence Energy Center Unit II).

Siemens Energy supplied electric generator for the Lawrence Energy Center (Lawrence Energy Center Unit III).

GE Power supplied steam boiler for the Lawrence Energy Center (Lawrence Energy Center Unit I).

GE Power supplied steam boiler for the Lawrence Energy Center (Lawrence Energy Center Unit II).

GE Power supplied steam boiler for the Lawrence Energy Center (Lawrence Energy Center Unit III).

For more details on Lawrence Energy Center, buy the profile here.

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.