Chihuido is an 871MW hydro power project. It is planned on Neuquen river/basin in Neuquen, Argentina. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 2029. Buy the profile here.
Description
The project is being developed and currently owned by Emprendimientos Hidroelectricos Sociedad del Estado ProvIncial.
The project is expected to generate 2,750 GWh of electricity.
Development status
Post completion of the construction, the project is expected to get commissioned in 2029.
Contractors involved
Chihuido (Chihuido I) will be equipped with LLC Inter Rao Engineering francis turbines. The phase consists of 4 turbines with 159.25MW nameplate capacity.
LLC Inter Rao Engineering is expected to supply 3 electric generators for the Chihuido (Chihuido I).
For more details on Chihuido, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.