Bui is a 400MW hydro power project. It is located on Volta river/basin in Brong-Ahafo, Ghana. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2009 and subsequently entered into commercial operation in 2013. Buy the profile here.
Description
The project is developed and owned by Bui Power Authority.
The project generated 969 GWh of electricity.
Development status
The project construction commenced in 2009 and subsequently entered into commercial operation in 2013.
Contractors involved
Sinohydro was selected to render engineering procurement construction services for the hydro power project.
GE Renewable Energy was selected as the turbine supplier for the hydro power project. The company provided 3 units of francis turbines, each with 133MW nameplate capacity.
GE Renewable Energy supplied 3 electric generators for the project. The generator capacity is 148 MVA.
For more details on Bui, buy the profile here.
Data Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.