Danish wind manufacturer Vestas has received wind turbine delivery orders for four renewable projects in China, Finland and Costa Rica.

Hebei Fengning Construction Investment New Energy has awarded a 50MW order to Vestas for the HECIC Fengning Senjitu Wind Farm Phase II project in China. The wind manufacturer is expected to make the deliveries and commission the turbines at the facility by the end of 2015.

The two Finnish projects for which Vestas will deliver wind turbines have generation capacities of 53MW and 23MW.

Finland’s EPV Tuulivoima has awarded the order for the 53MW wind project to Vestas, under which it will deliver, install and commission 16 of its V126-3.3MW turbine models for the Ilmajoki Santavuori project.

Deliveries for the project have been scheduled to take place by first quarter of 2016, following which the project will be commissioned by the third quarter.

The second Finnish order is for a 23MW wind project in Posio, Lappland and Kuusamo, Northern Ostrobothnia. E-Group has forwarded the order to the Danish firm for the Posio I project.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

Vestas will supply seven of its V126-3.3MW turbines for the facility, which will feature Vestas De-icing System. The firm is expected to start the deliveries in the second quarter of 2016.

The fourth order with Fila de Mogote, a subsidiary of US-based Hunt Energy Horizons (Hunt Oil), is for the 21MW Mogote wind power facility in Guanacaste province, Costa Rica.

Under the terms of the contract, Vestas will supply and install seven of its V90-3.0MW wind turbine models for the facility.

Deliveries for the wind farm will start from the third quarter this year.