French company Alstom has completed the installation of its new-generation offshore wind turbine, the 6-MW Haliade 150, off Ostend harbour at the Belwind site in Belgium.
The wind turbine, with energy yield 15% higher than existing turbines, features 150m rotor with blades stretching 73.50m and the 61m jacket placed on top of pillars, which have been sunk at a depth exceeding 60m.
Then the three elements of the 78m tower were gradually assembled on the jacket and the nacelle stands at a height of over 100m above sea level.
The turbine, which weighs about 1,500 tonnes and operates without a gearbox (using direct drive), can power around 5,000 households.
Alstom Wind senior vice president Alfonso Faubel said the project with Belwind asserts company’s technological leadership and innovative abilities.
"The installation of our turbine which is simple, robust and efficient thus contributing in boosting the competitiveness of offshore wind energy," added Faubel.

US Tariffs are shifting - will you react or anticipate?
Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.
By GlobalDataAlstom claims that Haliade 150 features the company’s PURE TORQUE design, which helps in protecting the generator by diverting unwanted mechanical stress towards the tower and optimises performance.
Belwind chairman Wim Biesemans said, "Belwind’s tried and tested expertise in completing offshore projects and setting up wind farms has helped Alstom to perform the installation work in sea waters under the best possible conditions."
The company has completed tests on the first Haliade 150 at Le Carnet site in France that was commissioned in March 2012. The Carnet wind turbine is expected to complete its final certification in the first half of 2014.
Alstom plans to complete the construction of the two factories in Saint-Nazaire in summer 2014 to produce nacelles and generators.
Later, Alstom will begin construction of the two Cherbourg factories to produce blades and towers.
___________________________________________________________________________________________
Image: Alstom’s Haliade 150- 6MW wind offshore turbine at Belwind site, Belgium. Photo: Courtesy of Alstom.