50Hertz has received official approval to construct a substation and a converter at the Mühlenbeck grid connection point, located in the municipality of Schossin, Mecklenburg-Western Pomerania, in northern Germany.
The immission control permit was issued by the State Office for Agriculture and Environment (StALU) Western Mecklenburg. It authorises the energy network operator to begin work on a development described as a critical component of Germany’s renewable energy infrastructure.
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
The upcoming facility at Mühlenbeck will bring together six power lines spanning extra-high, high and medium voltage levels.
Once operational, the site will support the integration of significant volumes of climate-neutral electricity produced in Mecklenburg-Western Pomerania, as well as from wind farms in the North and Baltic Seas.
This electricity will be transmitted to areas across Germany, supplying businesses, households and industry.
50Hertz CEO Stefan Kapferer said: “The Mühlenbeck grid connection point will become a key hub for the energy transition in northern Germany.
“In the future, we will bring large quantities of renewable electricity from here to where it is needed: to western Mecklenburg, the Hamburg metropolitan region and industrial sites in southern Germany. This will strengthen both security of supply and competitiveness.”
The permitted plans specify the construction of a substation equipped with 15 transformers and the installation of the first of three planned converters.
These converters are designed to change alternating current to direct current, which is required for transmitting large amounts of energy efficiently over long distances.
The setup is a crucial part of establishing links to the NordOstLink and SuedOstLink+ high-voltage direct-current connections.
50Hertz submitted its application for the project under the Federal Immission Control Act in November 2025.
Certain preparatory works, such as building an access road and initial site preparation, had previously received consent from the local authority.
The company expects to commence main construction activities at the beginning of 2027.
The Mühlenbeck grid connection point is considered one of Germany’s main infrastructure projects aimed at supporting the wider integration of renewable energy into the national grid.
The project responds to increasing demand for electricity transport from generation sites in the north to consumption centres in the west and south.